How we work
Our execution process
The step-by-step method our crews follow for a heavy transformer or locomotive shift.
Execution Timeline (16 Steps)
#1
Placement & Rails
Loco Trailer Entering Inside Plinth Zone
Phase Summary
Multi-axle hydraulic heavy trailer maneuvered onto site plinth.
Detailed Execution Procedure
Heavy multi-axle trailer carrying the locomotive/transformer is carefully guided onto the site plinth foundation area under constant ground spotter supervision.
Specialized Equipment Used
- Multi-Axle Heavy Trailer
- Ground Spotting Gear
- Level Steel Plates
Mandatory Safety Protocol
Ground bearing capacity and clearance checks performed.
Step 1 of 16 in Execution Chain